Saceem built a new wastewater pretreatment plant that opens in Cologne
Saceem was in charge of the construction of the wastewater pretreatment plant for the city of Colonia del Sacramento, which was inaugurated on October 10. The brand new infrastructure will treat liquid waste from the area.
The Mayor, Carlos Moreira, and the president of OSE, Raúl Montero, as well as other authorities, participated in the inauguration.
The project included the construction, operation and maintenance of the plant and ancillary works that are made up of a pumping station, a delivery line and an outfall for the disposal of effluents.
The work started in 2020 involved an investment of 8.5 million dollars from OSE and Montes del Plata. The execution and completion of this plant demonstrated, once again, Saceem's experience in hydraulic works.