Project, supply, electromechanical assembly and civil works necessary for the construction of 19,530 m of oil pipeline in steel pipe lined with polyethylene.
100% of welds radiographed according to API 1104 standard.
Buried pipe except crossing the Santa Lucía River, carried out within the structure of the new bridge.
Cathodic protection system, including monolithic joints.